Constructed in 2009, the upper and lower plazas were experiencing widespread leakage into the spaces below and required a major capital renovation project. Nicholson & Galloway was hired to perform the following work:
- 15,000 square feet of asphalt paving replacement
- 15,000 square feet of Siplast modified bitumen roofing system
- 3,500 square feet of granite cladding resetting and replacement
- 45 granite stair treads removed and reset
- 15,000 square feet of new reinforced concrete slab
- 70 linear feet of new trench drains
- 26 new roof drains
- 40 new exterior light fixtures
- 100 square feet of bluestone slabs reset on sidewalk