Battery Park City

Constructed in 2009, the upper and lower plazas were experiencing widespread leakage into the spaces below and required a major capital renovation project. Nicholson & Galloway was hired to perform the following work:

  • 15,000 square feet of asphalt paving replacement
  • 15,000 square feet of Siplast modified bitumen roofing system
  • 3,500 square feet of granite cladding resetting and replacement
  • 45 granite stair treads removed and reset
  • 15,000 square feet of new reinforced concrete slab
  • 70 linear feet of new trench drains
  • 26 new roof drains
  • 40 new exterior light fixtures
  • 100 square feet of bluestone slabs reset on sidewalk